The Grenfell Tower fire fundamentally changed UK building safety. Here's what the Inquiry found, what has changed, and what remains to be done.
17 December 20244 min readFire Safety Services
The Grenfell Tower Fire
The Grenfell Tower fire of 14 June 2017 was the deadliest structural fire in the United Kingdom since the Second World War. Seventy-two people died in and as a result of the fire, which began in a fourth-floor flat and spread rapidly up the exterior of the 24-storey tower in the Royal Borough of Kensington and Chelsea. The fire burned for approximately 60 hours and caused catastrophic damage to the building.
The Grenfell Tower Inquiry, chaired by Sir Martin Moore-Bick, examined the causes of the fire and the response to it. The Inquiry published its Phase 1 report in 2019 and its Phase 2 report in September 2024. Together, they provide the most comprehensive examination of a UK building fire ever conducted and have been the primary driver of building safety reform in the UK.
What Caused the Fire to Spread?
The Grenfell Tower Inquiry concluded that the primary cause of the external fire spread was the aluminium composite material (ACM) cladding panels installed during a refurbishment completed in 2016. The panels — which had a polyethylene core — were highly combustible and, once ignited, allowed fire to spread rapidly up and around the building's exterior, bypassing the internal fire compartmentation that would otherwise have contained the fire to lower floors.
The Inquiry also found that the fire spread was exacerbated by combustible insulation installed behind the cladding, the absence of effective cavity barriers that would have slowed the spread of fire within the cladding cavity, and the use of non-compliant window units.
The Stay-Put Strategy and Its Failure
Grenfell Tower operated a stay-put evacuation strategy — the standard approach for purpose-built blocks of flats under UK fire safety guidance at the time. Under stay-put, only residents in the flat of origin are expected to evacuate; other residents are advised to remain in their flats with doors closed.
The stay-put strategy failed at Grenfell because the external fire spread meant that upper-floor residents faced fire and smoke conditions that made escape increasingly dangerous or impossible. The London Fire Brigade issued advice to evacuate at 02:47 — nearly two hours after the fire started. The Inquiry found that this delay cost lives.
The key lesson from Grenfell is that stay-put strategies are only safe where compartmentation — including external wall fire safety — is intact. External cladding that allows fire to bypass internal compartmentation renders stay-put unacceptable.
Key Lessons for Building Safety
The Grenfell Tower Inquiry identified a series of systemic failures with implications for the entire built environment sector:
External wall fire safety — combustible cladding and insulation on buildings over 18 metres presents an unacceptable fire risk. The government's ban on combustible materials in external walls of tall buildings (regulation 7(2)) was extended and strengthened following Grenfell.
Regulatory failure — the Inquiry found that the building regulations and their supporting guidance were inadequate, unclear, and had been weakened by successive deregulatory reforms. The Building Safety Act 2022 was introduced in direct response to these findings.
Competence — the Inquiry identified widespread competence failures across the construction industry, from architects and contractors to building control inspectors and fire safety consultants. The Building Safety Act introduces enhanced competence requirements for those working on higher-risk buildings.
Golden thread of information — critical information about building materials and fire safety provisions was not maintained or accessible. The Building Safety Act's golden thread requirement addresses this directly.
Resident voice — residents of Grenfell Tower had raised fire safety concerns for years before the fire. Those concerns were not adequately addressed. The Building Safety Act gives residents new rights to information and to raise safety concerns.
What Has Changed Since Grenfell?
The regulatory and legislative response to Grenfell has been extensive. The Building Safety Act 2022 introduced the Building Safety Regulator, the gateway process, the golden thread of building information, and new duties for accountable persons. Regulation 7(2) now bans combustible materials in the external walls of buildings over 18 metres. The EWS1 and PAS 9980 frameworks were introduced to address existing buildings with potentially dangerous external wall systems. The government's cladding remediation programme has committed billions of pounds to removing dangerous cladding from residential buildings.
Despite this progress, significant challenges remain. Many buildings with dangerous cladding have not yet been remediated. The competence framework for the construction industry is still developing. And the human cost of Grenfell — 72 lives lost, hundreds of survivors and bereaved families — is a permanent reminder of what is at stake when fire safety is not taken seriously.
Frequently Asked Questions
What type of cladding caused the Grenfell Tower fire?
The external fire spread at Grenfell was caused primarily by aluminium composite material (ACM) cladding panels with a polyethylene core, installed during a 2016 refurbishment. The panels were highly combustible and allowed fire to spread rapidly up the building's exterior.
Is ACM cladding now banned in the UK?
Regulation 7(2) of the Building Regulations bans the use of combustible materials — including ACM with a polyethylene core — in the external walls of buildings over 18 metres. The ban applies to new buildings and to refurbishments of existing buildings.
What is the government doing about existing buildings with dangerous cladding?
The government has committed significant funding to the cladding remediation programme, requiring major developers to remediate buildings they built or refurbished with dangerous cladding. The Building Safety Regulator has powers to require remediation where developers do not act voluntarily.
Can residents find out what their building's external wall is made of?
Residents of higher-risk buildings have a right to information about their building under the Building Safety Act 2022, including fire safety information. For buildings that have had a PAS 9980 FRAEW, the FRAEW report will identify the external wall materials.
What should I do if I am concerned about cladding on my building?
Contact your freeholder or managing agent and request information about the building's external wall fire safety position. If an EWS1 form or PAS 9980 FRAEW has not been obtained, request that one is commissioned. If you do not receive a satisfactory response, you can raise concerns with the Building Safety Regulator.
Need fire safety advice for your project?
Our dedicated fire engineering team responds to all enquiries within 1 to 2 working days.